Cost, price, and value. These are three distinct terms that often catch out quantity surveyors early in their careers. However, being able to distinguish them is vital.
So, in this video, I’m going to break it down into simple terms. Cost vs Price vs Value.
1. What Is Cost in Construction?
Cost is what the contractor pays for completing the works, the labor, plant, materials, and overheads. It’s the contractor’s actual spend.
Metroun LearningShort courses with structured CPD, 20 minutes eachStart ›Let’s say you’re building a small brick boundary wall.
The materials, labour, and equipment all add up to a cost of 1,650 lb.
This is the total amount of money the contractor will pay to complete the works.
2. What Is Price in Construction?
Price is the amount a contractor charges for carrying out the works. Usually based on the anticipated cost plus an allowance for profit and risk.
Take that same wall, for example.
The contractor adds 20% to cover profit and risk and quotes just under 2,000 lb.
But, here’s the thing.
The price isn’t fixed by the cost.
Ask three contractors to quote for the same wall on the same day, and you’ll get three different prices.
Example: Three contractors, same brick wall
Contractor A
£1,850
Competitive price
Contractor B
£2,000
Different quotation
Contractor C
£2,400
Higher price
One wants the works and submits a competitive price at 1,850 lb. Another is at 2,400 lb.
Same wall, different prices.
It’s not just the anticipated cost that affects the price. It’s also how each contractor reads the market, assesses the risk, and decides how much they want the job.
The cost is what the contractor will pay. The price is what they will receive for completing the works, and the difference between the price and cost is the contractor’s margin.
If you’re working on a cost reimbursable contract, the price will increase or decrease depending on the cost.
If you’re working on a fixed price or lump-sum contract, the price is fixed, and the risk of cost fluctuation sit with the contractor.
3. What Is Value in Construction?
Value. This is the one people sometimes get wrong.
Value isn’t the cost, and it isn’t the full price.
Value is the amount the completed work is worth under the contract at a specific date.
Let’s use the wall as an example.
The agreed price is £2,000 for the finished job. You turn up at the end of day one and the wall is half built.
The value of work done is roughly £1,000.
Brick wall — interim valuation
50% complete
Value of work completed
£1,000
Agreed contract price
£2,000
The wall isn’t finished, so the contractor hasn’t earned the full price.
That’s exactly what happens in an interim valuation.
On larger projects, the QS measures what’s actually been completed up to the valuation date and assesses its value under the contract.
4. Cost vs Price vs Value: The Key Differences
- Cost is what the contractor spends.
- The price is what the client agrees to pay.
- The value is the assessed amount of work completed at a particular point in time.
5. What Does Value Mean in Value Engineering?
It’s worth noting that value can have another meaning in construction, which you’ll see used for things like value management or value engineering.
In that context, value means benefit relative to cost, i.e. getting the most function or performance for the money spent.
It’s about making smart design and specification decisions.