Understanding the Supplemental Provisions in the JCT Design and Build Contract

The JCT Design and Build Contract contains a series of optional “Supplemental Provisions” within Schedule 2. These provisions are often
Battle of Forms

“Battle of forms” is a common contractual issue in construction procurement where two parties attempt to contract on their own
Adjudication in Construction: Step by Step (With Real Timeframes)

Adjudication is one of those processes every QS knows exists… But when it actually lands on a job, it suddenly
NEC: An introduction to ‘Acceleration’

What is Acceleration? Acceleration is the process of bringing forward Completion or Key Dates compared to the Accepted Programme. It
NEC4 ECC – Contractor’s Design Responsibility Explained

Under NEC4 ECC, contractor’s design responsibility is one of the most misunderstood areas of the contract and one that regularly
Fit for Purpose: The Clause QSs Should Never Let Slip Through

If you’ve assessed construction contracts, you’ve definitely seen it. Buried in a spec… tucked into Employer’s Requirements… sometimes even sitting
NEC4 ECC Scope Explained

Introduction If you’re working under an NEC4 Engineering and Construction Contract, the Scope, (or Works Information if you’re working under
Alternative A vs Alternative B: How Gross Valuation Works under JCT DB 2024

If you work with JCT Design and Build, one of the key payment choices at tender or contract stage is
What Laptop Should a Quantity Surveyor Actually Buy?

Let’s be honest, most QSs don’t care about laptop until theirs starts lagging halfway through a cost plan. You’re in
What Are Overheads and Profit in Construction?

When thinking of the cost to complete a construction project, your mind is immediately drawn to the obvious stuff, like
