How QSs Can Add Value Before the Project Starts

A Quantity Surveyor’s role should not begin when the first payment application is due. The value of a QS can
6 Things Quantity Surveyors Should Track Every Week

Good commercial management does not happen once a month. While monthly reports, CVRs and formal valuations are important, the best
What Is a Novation Agreement in Construction?

A novation agreement is a legal document that transfers one party’s rights and obligations under a contract to another party.
Understanding the Supplemental Provisions in the JCT Design and Build Contract

The JCT Design and Build Contract contains a series of optional “Supplemental Provisions” within Schedule 2. These provisions are often
Battle of Forms

“Battle of forms” is a common contractual issue in construction procurement where two parties attempt to contract on their own
Adjudication in Construction: Step by Step (With Real Timeframes)

Adjudication is one of those processes every QS knows exists… But when it actually lands on a job, it suddenly
NEC: An introduction to ‘Acceleration’

What is Acceleration? Acceleration is the process of bringing forward Completion or Key Dates compared to the Accepted Programme. It
NEC4 ECC – Contractor’s Design Responsibility Explained

Under NEC4 ECC, contractor’s design responsibility is one of the most misunderstood areas of the contract and one that regularly
Fit for Purpose: The Clause QSs Should Never Let Slip Through

If you’ve assessed construction contracts, you’ve definitely seen it. Buried in a spec… tucked into Employer’s Requirements… sometimes even sitting
NEC4 ECC Scope Explained

Introduction If you’re working under an NEC4 Engineering and Construction Contract, the Scope, (or Works Information if you’re working under
