Concrete Foundations

How to Calculate Concrete for Foundations (Pads, Strips & Rafts)

Concrete foundations are one of the first things QSs are asked to measure, and one of the easiest places to make mistakes.

This guide breaks down how to calculate concrete quantities for the three most common foundation types:

  • Pad foundations
  • Strip foundations
  • Raft foundations

The Basic Formula (Always Start Here)

For all concrete foundations, the core calculation is:

Volume (m³) = Length × Width × Depth

The difference between pad, strip and raft foundations is simply how those dimensions are defined.


1. How to Calculate Concrete for Pad Foundations

Pad foundations are usually square or rectangular bases supporting columns.

What you need

  • Length (m)
  • Width (m)
  • Depth / thickness (m)
  • Number of pads

Worked example

One pad foundation:

  • Length = 1.2 m
  • Width = 1.2 m
  • Depth = 0.6 m

Concrete volume (per pad):
1.2 × 1.2 × 0.6 = 0.864 m³

If there are 10 identical pads:

  • 0.864 × 10 = 8.64 m³

QS tips

  • Check if pads vary in size — don’t assume they’re all identical
  • Watch for stepped pads or thickenings
  • Confirm if blinding concrete is measured separately

2. How to Calculate Concrete for Strip Foundations

Strip foundations run continuously under walls.

What you need

  • Total strip length (m)
  • Strip width (m)
  • Concrete depth (m)

Worked example

Strip foundation:

  • Length = 22 m
  • Width = 0.6 m
  • Depth = 0.3 m

Concrete volume:
22 × 0.6 × 0.3 = 3.96 m³

QS tips

  • Measure centre-line or net length consistently
  • Watch junctions and returns — don’t double count
  • Check drawings for local deepening at load points

3. How to Calculate Concrete for Raft Foundations

Raft foundations are essentially large slabs covering the full footprint of the building.

What you need

  • Raft length (m)
  • Raft width (m)
  • Raft thickness (m)

Worked example

Raft foundation:

  • Length = 12 m
  • Width = 8 m
  • Thickness = 0.35 m

Concrete volume:
12 × 8 × 0.35 = 33.6 m³

QS tips

  • Check for thickened edges or beams within the raft
  • Allow separately for upstands and ground beams
  • Confirm whether blinding is included or excluded

Allowances QSs Must Not Forget

1. Wastage

Typical allowances:

  • Small pours: 5–10%
  • Complex foundations: up to 10%

Always confirm whether the rate already includes wastage.


2. Over-excavation

Excavations are rarely perfect:

  • Sides collapse
  • Trenches widen
  • Formation levels vary

Concrete quantities often increase slightly on site — this risk should be recognised.


3. Blinding Concrete

Blinding is usually:

  • 50–75 mm thick
  • Measured separately

Don’t accidentally include it in structural concrete quantities.


Common QS Mistakes to Avoid

  • Mixing excavation depth with concrete depth
  • Forgetting pad numbers
  • Ignoring stepped foundations
  • Measuring raft concrete but missing thickened edges
  • Assuming drawings are perfectly coordinated

How QSs Sense-Check Concrete Quantities

A quick sense check:

  • Pad foundations: usually 0.5–1.5 m³ each
  • Strip foundations: roughly 0.15–0.25 m³ per linear metre
  • Raft foundations: slab volume + local thickenings

If your numbers feel wildly outside this range — recheck.


Conclusion

Concrete calculations aren’t about complicated maths.

They’re about:

  • Reading drawings carefully
  • Applying consistent logic
  • Understanding site reality

Get those right, and your quantities will stand up commercially and technically.

Metroun Learning
 
Looking for training? Metroun has you covered. Online courses that can fit into your busy schedule. Formal CPD recognised.
Metroun Consultants
 
Need a QS? Professional Quantity Surveyors ready to go. We handle the numbers. You focus on the big picture.
APC Support
 
Dedicated MRICS counsellors, with you every step of your APC journey.

Subscribe to our newsletter

Sign up to our newsletter to receive all the latest updates.

More articles for you

NEC4 ECC Scope Explained
1 April 2026

Introduction If you’re working under an NEC4 Engineering and Construction Contract, the Scope, (or Works Information if you’re working under