How to Calculate Cement, Sand & Aggregate for Concrete | Step by Step Guide

Concrete Slab Calculation

Concrete is a mixture of cement, sand (fine aggregate), and gravel (coarse aggregate), and each component has a specific role in creating a durable and strong slab. If you’re planning a concrete slab for a project, understanding how to calculate the quantities of materials needed is crucial to avoid wastage or shortfalls.

Here’s a step-by-step guide to calculating the sand, cement, and aggregate required for a 10m x 10m x 200mm (0.2m) concrete slab.

Step 1: Determine the Volume of the Concrete

The first step is to calculate the total volume of the concrete slab. This is done by multiplying the length, width, and thickness of the slab:

Volume = Length × Width × Thickness

Given dimensions:

  • Length = 10m
  • Width = 10m
  • Thickness = 0.2m

Volume = 10m × 10m × 0.2m = 20 cubic meters(m3)

Step 2: Choose the Concrete Mix Ratio

Concrete mix ratios vary based on the strength requirement, but for a general slab, a common mix ratio is 1:2:4. This means:

  • 1 part cement
  • 2 parts sand (fine aggregate)
  • 4 parts gravel (coarse aggregate)

This mix ratio is commonly used for medium-strength concrete (M20 grade concrete).

Step 3: Calculate Total Dry Volume of Concrete

When calculating the materials for concrete, the wet concrete volume needs to be converted to a dry volume. This is because cement, sand, and aggregates will increase in volume once mixed. To adjust for this, we multiply the volume by a factor of 1.54 (this accounts for bulking and shrinkage).

Dry Volume=Wet Volume×1.54

Volume=20m3×1.54=30.8m3

Step 4: Calculate Cement, Sand, and Aggregate Quantities

Now that we know the total dry volume, we can calculate the quantities of cement, sand, and aggregate based on the chosen mix ratio (1:2:4).

Cement Quantity:

For the 1:2:4 mix, cement is 1 part out of the total 7 parts (1 + 2 + 4 = 7).

Cement Volume = (1/7)×30.8 m3=4.4 m3

To convert the volume of cement into bags (assuming 1 bag of cement = 0.035 m³) or a 50kg bag:

Cement Bags=4.4 m3 / 0.035 m3/bag =126 bags

Sand Quantity:

For sand, it’s 2 parts out of 7 parts.

Sand Volume=(2/7)×30.8 m3=8.8 m3

Aggregate Quantity:

For gravel (aggregate), it’s 4 parts out of 7 parts.

Aggregate Volume=(4/7)×30.8 m3=17.6 m3

Step 5: Final Quantities for the Concrete Slab

To summarize, for a 10m x 10m x 200mm concrete slab with a 1:2:4 mix, you will need:

  • Cement: 126 50kg bags (approx. 4.4 m³)
  • Sand: 8.8 m³
  • Aggregate: 17.6 m³

Step 6: Additional Considerations

  • Water: The water-cement ratio is typically around 0.5 for a mix like this, but the exact amount will depend on the desired workability.
  • Wastage: Always account for about 5-10% extra material to cover spillage and other losses.

This method ensures that you have the correct quantities of each material, avoiding overuse or shortages, and helping to achieve a strong and durable concrete slab for your project.